SAP C_TS412_1909 Exam Description:
The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.
C_TS412_1909 Exam Certification Details:
| Cut Score: | 51% |
| Exam: | 80 questions |
| Duration: | 180 mins |
| Languages: | English |
| Level: | Associate |
| Sample Questions: | SAP C_TS412_1909 Exam Sample Question |
SAP C_TS412_1909 Certification Exam Topics:
| Topic Areas | Topic Details, Courses, Books |
|---|---|
| Material > 12% | Explain Work breakdown structure BOM, BOM PS Interface, component assignment in the network, material procurement |
| Reporting < 8% | Determine general reporting requirements and reporting requirements for cost centers. Configure cost center reporting and create report painter reports |
| Resources > 12% | Describe how the Resource Planning process integrates with HCM |
| Revenues and Payments > 12% | Describe the characteristics of Revenues & Payments. |
| Dates > 12% | Describe the importance of various dates which can be tracked for projects |
| Cost and Budgets > 12% | Describe procedures for establishing budgets and reporting costs. |
| Project Structures > 12% | Name the components of Work Breakdown Structure, Network and activities, Milestones |
NEW QUESTION 18
You have created an internally-processed network activity, and assigned a work center and the work.
After saving, you discover that no planned costs are displayed in the cost element report for the activity.
What could be the reason? Note: There are 3 correct Answers to this question.
- A. The formula for costing in the work center is incorrect.
- B. Integrated planning for the network is active.
- C. The duration is missing in the activity.
- D. The activity output price for the activity type and cost center assigned to the work center is not maintained.
- E. The Determine Costs indicator in the network header rules out planned cost calculation.
Answer: C,D,E
NEW QUESTION 19
You have activated the workflow for confirmation variances in SAP Project System. Who is the receiver of this workflow item?
- A. The person responsible for the superior WBS element
- B. The MRP controller for the network
- C. The person responsible for the network activity
- D. The person responsible for the work center
Answer: B
NEW QUESTION 20
You are working with networks and WBS elements. Which of the following statements applies?
- A. You can assign the network header to multiple WBS elements.
- B. You can reassign an activity from one network to another.
- C. You have to maintain a network profile in the project profile.
- D. You have to activate the operative indicator Account Assignment Element for WBS elements with activities.
Answer: A,B
NEW QUESTION 21
A customer needs to analyse the capacity requirements of their network activities. Which reports do you recommend? Note: There are 2 correct Answers to this question.
- A. Structure information system reports
- B. Cost element reports
- C. Resource reports
- D. Hierarchical reports
Answer: A
NEW QUESTION 22
You used reductions to reduce the scheduled duration of all internally-processed activities in your project. However, the duration did not changed after overall network scheduling.
What do you check? Note: There are 2 correct Answers to this question.
- A. If the reduction strategy is set in the network header
- B. If the reduction strategy is set in each activity
- C. If the appropriate reduction type is set in the parameters for network scheduling
- D. If the maximum reduction level is less than 100
Answer: A,C
NEW QUESTION 23
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.
- A. Controlling area
- B. Sales organization
- C. Operating concern
- D. Company code
- E. Plant
Answer: A,D,E
NEW QUESTION 24
Which of the following is visible in the project planning board? Note: There are 2 correct Answers to this question.
- A. Project-relevant purchase orders
- B. Capacity requirements
- C. Production orders assigned to WBS elements
- D. Maintenance orders assigned to an activity
Answer: B,D
NEW QUESTION 25
The system status of a WBS element is created (CRTD). Which business process is allowed for this WBS element?
- A. Activity allocation
- B. Goods receipt for purchase orders
- C. Creation of purchase orders
- D. Calculation of actual values
Answer: C
NEW QUESTION 26
What PP/DS master data is necessary for using PP/DS? Note: There are 2 correct Answers to this question.
- A. Location
- B. Production version
- C. Resource
- D. Material
Answer: A,C
NEW QUESTION 27
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.
- A. Preliminary purchase requisition for WBS element
- B. Planned order
- C. Third-party order
- D. Reservation for WBS element
- E. Purchase requisition and Reservation for WBS element
Answer: A,D,E
NEW QUESTION 28
Which statements describe planned and actual revenue for WBS elements? Note: There are 2 correct Answers to this question.
- A. Actual revenue is posted via a billing plan assigned to a WBS element.
- B. Planned revenue can be transferred from a sales quotation.
- C. Planned revenue requires a sales order assigned to a WBS element.
- D. Actual revenue is posted via a billing document created from a sales order
Answer: B,D
NEW QUESTION 29
You use networks and internal activities in your project. You have activated capacity requirements and notice that one work center is overloaded. You have no authorization to change the work center. How can you reduce the overload of the work center? Note: There are 2 correct Answers to this question.
- A. Trigger automatic capacity leveling inside the project planning board.
- B. Maintain subordinate internal activity elements assigned to other work centers.
- C. Increase the capacities of the work center in the project planning board.
- D. Shift activities backward or forward on the time axis where more capacities are available.
Answer: A,D
NEW QUESTION 30
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
- A. Enter an offset of 10 days to the start date of the activity.
- B. Enter February 10 as fixed date.
- C. Enter an offset of -18 days to the finish date of the activity.
- D. Enter 10 days as duration.
Answer: B
NEW QUESTION 31
How can you search in the structure overview based on the user status? Note: There are 2 correct Answers to this question.
- A. By searching via status selection profile
- B. By searching for the individual status
- C. By searching for the status profile
- D. By searching via status combination code
Answer: B,C
NEW QUESTION 32
Which of the following actions can transfer actual costs for external processing? Note: There are 2 correct Answers to this question.
- A. Saving a service entry sheet
- B. Saving a purchase order
- C. Saving a goods receipt
- D. Saving a supplier invoice
Answer: A,C
NEW QUESTION 33
Which of the following factors influence the scheduling of internal processing activities? Note: There are
3 correct Answers to this question.
- A. The relationships between activity elements
- B. The factory calendar in the work center used for the internal processing activity
- C. The unit (for example, hour, day) of the field Normal Duration field of the activity
- D. An activated Scheduling indicator in the control key of the internal processing activity
- E. Whether the work for the internal activity is greater than its duration
Answer: A,B,D
NEW QUESTION 34
Which sales documents can update planned revenues on WBS elements? Note: There are 2 correct Answers to this question.
- A. Sales order
- B. Billing
- C. Inquiry
- D. Quotation
Answer: A,D
NEW QUESTION 35
You want to use billing for a customer project. Which customizing object controls the billing of sales order items?
- A. Requirements type
- B. Schedule line category
- C. Requirements class
- D. Item category
Answer: D
NEW QUESTION 36
Which of the following business processes do NOT lead to the booking of actual costs to an object?
Note: There are 2 correct Answers to this question.
- A. Goods receipt into unvaluated project stock
- B. Goods receipt of a non-stock item
- C. Goods receipt into valuated project stock
- D. Recording of external services in the service entry sheet
Answer: A,D
NEW QUESTION 37
What are the prerequisites for delivering materials from the project? Note: There are 2 correct Answers to this question.
- A. A shipping point is necessary.
- B. A sold to party is necessary.
- C. A sales order must be created in advance.
- D. A delivery document type must be configured.
Answer: A,B
NEW QUESTION 38
Your customer's projects are subject to recurring changes of date. The assembly activity has an earliest start date of February 10 and lasts until February 20. The customer wants to assign a material component so that this will be in stock 5 days in advance. Note: Every day is a working day. What do you recommend to set up the requirement date for the component?
- A. Set up the requirement date aligned with the activity start date and a negative offset of 5 days.
- B. Set up the requirement date manually as February 5.
- C. Set up the requirement date aligned with the activity finish date and an offset of 15 days.
- D. Set up the requirement date aligned with the activity start date and an offset of 5 days.
Answer: D
NEW QUESTION 39
......